Harbor Master Pump Station

Client: 
Tahoe City Public Utility District
Key staff: 
Project Manager – Walter R. Auerbach, P.E., Project Engineer – Project Surveyor - Keith Masuda, P.E., P.L.S

Project Description: Construction of  a replacement sewer pump station for the Grove Street Pump Station including the construction of a new Harbormaster building. This project included a new pump station and associated gravity sewer line, 305’ of 30” sewer line and 615’ of 6” dual force main connecting to an existing sewer main under SR 28.
 

Services Included:

  • Project Management
  • Construction Document Preparation
  • Agency approval/permitting
  • Bid Phase Services
  • Construction Inspection

Status: Completed 2008